Beginning of gasification in the municipality of Celestynów
“Today we can begin construction of a gas network that will provide access to gas fuel for almost the entire locality. We envisaged connecting about 100 customers within the framework of the agreement concluded with the contractor in August of this year, and at the moment we have more than 70 connection agreements, and more applications are under consideration – and I strongly encourage you to submit more”, stated Ireneusz Krupa.
By the end of 2023, Polska Spółka Gazownictwa will build a total of about 7.5 km of gas mains and at least 100 connections under a contract worth about PLN 1.24 million gross. To date, about 68 km of gas mains and about 1,400 connections have been built in the municipality of Celestynów.